August 18, 2020
Megan A. Elliott
MGKF Litigation Blog
On August 10, 2020, the Ninth Circuit reversed a lower court’s grant of defendants’ motion for summary judgement, permitting plaintiffs’ case to move forward in a Superfund action for contribution. See Arconic v. APC Investment, No. 19-55181 (9th Cir. Aug. 10, 2020), a case we had reported on here. At issue was whether a settlement between plaintiffs and certain de minimis parties for future potential response costs was an adequate triggering event for the statute of limitations period (against different defendants) in an action for contribution under CERCLA Section 113(f). The Ninth Circuit held that it was not, explaining that in the context of a “judicially approved settlement,” the proper triggering event was a settlement which imposed actual cleanup costs in excess of a party’s estimated liability at the site.
Read the full blog post.